Dept. of Trans. PROGRESS Serial No. Contract No. 06-024-11-07 01-311714 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 47% 31% 01-DN-169-2.3/2.9 Federal Project: ACBR-S169(4) STP-S169(4) Progress payment No. 13 Payment period ending: 01-20-06 SHASTA CONSTRUCTORS INC P O BOX 491539 REDDING CA 960491539 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,234,346.59 0.00 2.a. Extra Work 165,267.55 0.00 b. Adjustment Comp. -5,000.00 0.00 3. Materials on Hand 307,568.82 0.83 4. Earned Subject to Retention 1,702,182.96 0.83 5. Mobilization 329,650.00 0.00 6. Total Work Completed 1,724,264.14 7. Deductions -16,323.46 19,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,015,509.50 19,000.83 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 19,000.83