Dept. of Trans. PROGRESS Serial No. Contract No. 06-142-15-10 01-311714 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 48% 31% 01-DN-169-2.3/2.9 Federal Project: ACBR-S169(4) STP-S169(4) Progress payment No. 17 Payment period ending: 05-19-06 SHASTA CONSTRUCTORS INC P O BOX 491539 REDDING CA 960491539 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,293,619.09 34,492.50 2.a. Extra Work 174,257.26 2,979.88 b. Adjustment Comp. -5,000.00 0.00 3. Materials on Hand 307,568.82 0.00 4. Earned Subject to Retention 1,770,445.17 37,472.38 5. Mobilization 347,000.00 0.00 6. Total Work Completed 1,809,876.35 7. Deductions -21,458.18 -5,344.92 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,095,986.99 32,127.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 32,127.46