Dept. of Trans. PROGRESS Serial No. Contract No. 07-052-11-25 01-314404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 67% 60% 01-HUM-101-56.2/57.5 Federal Project: ACNH-Q101(97) Progress payment No. 21 Payment period ending: 02-20-07 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,341,833.13 0.00 2.a. Extra Work 712,925.49 48,116.35 b. Adjustment Comp. 122,334.77 -260.09 3. Materials on Hand 28,726.01 0.00 4. Earned Subject to Retention 8,205,819.40 47,856.26 5. Mobilization 1,144,625.00 0.00 6. Total Work Completed 9,321,718.39 7. Deductions -8,015.59 2,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 9,342,428.81 49,856.26 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 49,856.26