Dept. of Trans. SEMI-FINAL Serial No. Contract No. 01-003-12-06 01-329424 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 01-MEN-101-93.6/94.0 Federal Project: NONE Progress payment No. 30 Payment period ending: 07-11-00 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01105 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,297,122.70 1,730.17 2.a. Extra Work 1,086,810.53 32,118.07 b. Adjustment Comp. 33,467.73 0.00 3. Materials on Hand 4. Earned Subject to Retention 4,417,400.96 33,848.24 5. Mobilization 372,414.00 0.00 6. Total Work Completed 4,789,814.96 7. Deductions -10,000.00 0.00 8. a.Contract Retentions -205,446.19 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 205,446.19 0.00 9. Total pay to Contractor 4,779,814.96 33,848.24 10. Reduction Amt to Escrow -200,000.00 0.00 11. Payment to Escrow 200,000.00 12. Net Pymt. this Estimate 33,848.24