Dept. of Trans. SEMI-FINAL Serial No. Contract No. 01-017-09-05 01-329424 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 01-MEN-101-93.6/94.0 Federal Project: NONE Progress payment No. 31 Payment period ending: 07-11-00 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01105 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,297,122.70 0.00 2.a. Extra Work 1,142,694.01 55,883.48 b. Adjustment Comp. 25,482.27 -7,985.46 3. Materials on Hand 4. Earned Subject to Retention 4,465,298.98 47,898.02 5. Mobilization 372,414.00 0.00 6. Total Work Completed 4,837,712.98 7. Deductions -10,000.00 0.00 8. a.Contract Retentions -205,446.19 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 205,446.19 0.00 9. Total pay to Contractor 4,827,712.98 47,898.02 10. Reduction Amt to Escrow -200,000.00 0.00 11. Payment to Escrow 200,000.00 12. Net Pymt. this Estimate 47,898.02