Dept. of Trans. PROGRESS Serial No. Contract No. 10-082-13-55 01-363204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 94% 69% 01-HUM-101-R48.7/56.3 Federal Project: ACNH-Q101(149) Progress payment No. 10 Payment period ending: 03-22-10 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,683,486.36 43,417.50 2.a. Extra Work 306,970.97 62,363.68 b. Adjustment Comp. -43,208.03 142,027.58 3. Materials on Hand 0.00 -3,803.91 4. Earned Subject to Retention 12,947,249.30 244,004.85 5. Mobilization 425,000.00 0.00 6. Total Work Completed 13,372,249.30 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 13,372,249.30 244,004.85 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 244,004.85