Dept. of Trans. SEMI-FINAL Serial No. Contract No. 10-322-13-05 01-363204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 01-HUM-101-R48.7/56.3 Federal Project: ACNH-Q101(149) Progress payment No. 17 Payment period ending: 07-14-10 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,907,485.11 6,500.00 2.a. Extra Work 838,639.26 0.00 b. Adjustment Comp. -33,208.03 10,000.00 3. Materials on Hand 4. Earned Subject to Retention 13,712,916.34 16,500.00 5. Mobilization 425,000.00 0.00 6. Total Work Completed 14,137,916.34 7. Deductions -10,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 14,127,916.34 16,500.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 16,500.00