Dept. of Trans. FINAL Serial No. Contract No. 10-230-14-30 01-364314 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 01-MEN-20-2.7/32.7 Federal Project: NONE Progress payment No. 07 Payment period ending: 06-02-10 KAPEL CONSTRUCTION INC 130 FLOWER MCNIEL ROAD WILLOW CREEK CA 95573 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 403,478.60 0.00 2.a. Extra Work 58,992.79 0.00 b. Adjustment Comp. 3,000.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 465,471.39 0.00 5. Mobilization 25,000.00 0.00 6. Total Work Completed 490,471.39 7. Deductions 0.00 1,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 490,471.39 1,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,000.00