Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 05-271-15-00 01-365004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 01-MEN-128-R28.1/28.3 Federal Project: ACST-P128(41) P-P128(41) Progress payment No. 11 Payment period ending: 09-16-05 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,488,708.20 73,816.00 2.a. Extra Work 27,797.57 0.00 b. Adjustment Comp. 95,200.80 4,976.80 3. Materials on Hand 4. Earned Subject to Retention 1,611,706.57 78,792.80 5. Mobilization 175,000.00 0.00 6. Total Work Completed 1,786,706.57 7. Deductions -34,000.00 -29,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,752,706.57 49,792.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 49,792.80