Dept. of Trans. PROGRESS Serial No. Contract No. 24-114-15-32 01-366004 PROGRESS PAYMENT VOUCHER %complete: %time: 21% 18% Location: Federal Project: 01-HUM-101-80.0/84.0 ACNH-394(E) Progress payment No. 010 Payment period ending: 04-20-24 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,137,781.26 9,500.00 2. a. Extra Work 218,224.53 3,786.19 b. Adustment Comp. 3. Materials on Hand 783,423.79 -970.87 4. Earned Subject to Retention 7,139,429.58 12,315.32 5. Mobilization 3,750,000.00 0.00 6. Total Work Completed 10,106,005.79 7. Deductions -254,710.02 -3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,634,719.56 9,315.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 9,315.32