Dept. of Trans. PROGRESS Serial No. Contract No. 24-240-09-01 01-366004 PROGRESS PAYMENT VOUCHER %complete: %time: 33% 32% Location: Federal Project: 01-HUM-101-80.0/84.0 ACNH-394(E) Progress payment No. 013 Payment period ending: 08-20-24 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,922,330.59 2,324,230.77 2. a. Extra Work 337,593.47 55,359.80 b. Adustment Comp. 3. Materials on Hand 968,140.49 -383,434.70 4. Earned Subject to Retention 12,228,064.55 1,996,155.87 5. Mobilization 4,750,000.00 0.00 6. Total Work Completed 16,009,924.06 7. Deductions -328,832.70 -6,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 16,649,231.85 1,990,155.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,990,155.87