Dept. of Trans. PROGRESS Serial No. Contract No. 20-267-15-47 01-3660U4 PROGRESS PAYMENT VOUCHER %complete: %time: 13% 1% Location: Federal Project: 01-HUM-255-6.0/7.6 ACST-P255(11) Progress payment No. 001 Payment period ending: 09-20-20 STEELHEAD CONSTRUCTORS JV PO BOX 536 PALO CEDRO CA 96073 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 246,002.20 246,002.20 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 246,002.20 246,002.20 5. Mobilization 142,500.00 142,500.00 6. Total Work Completed 388,502.20 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 388,502.20 388,502.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 388,502.20