Dept. of Trans. PROGRESS Serial No. Contract No. 24-087-11-50 01-3660U4 PROGRESS PAYMENT VOUCHER %complete: %time: 88% 75% Location: Federal Project: 01-HUM-255-6.0/7.6 ACST-P255(11) Progress payment No. 028 Payment period ending: 03-20-24 STEELHEAD CONSTRUCTORS JV PO BOX 536 PALO CEDRO CA 96073 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,386,795.63 15,050.00 2. a. Extra Work 102,469.09 0.00 b. Adustment Comp. 194,094.30 191,571.21 3. Materials on Hand 4. Earned Subject to Retention 2,683,359.02 206,621.21 5. Mobilization 285,000.00 0.00 6. Total Work Completed 2,968,359.02 7. Deductions -168,000.00 1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,800,359.02 207,621.21 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 207,621.21