Dept. of Trans. PROGRESS Serial No. Contract No. 00-326-09-58 01-378004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 0% 13% 01-MEN-1-59.9/60.6 Federal Project: ACBR-P001(440) STP-P001(440) Progress payment No. 09 Payment period ending: 11-20-00 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01463 Total Estimate This Estimate 1. Contract Itms Without Mobil. 59,536.00 13,160.00 2.a. Extra Work 48,040.10 1,495.91 b. Adjustment Comp. 3. Materials on Hand 700,066.83 0.00 4. Earned Subject to Retention 807,642.93 14,655.91 5. Mobilization 6. Total Work Completed 107,576.10 7. Deductions 8. a.Contract Retentions -80,764.29 -1,465.59 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 726,878.64 13,190.32 10. Reduction Amt to Escrow 11. Payment to Escrow 80,760.00 12. Net Pymt. this Estimate 13,190.32