Dept. of Trans. PROGRESS Serial No. Contract No. 02-267-11-49 01-378014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 19% 13% 01-MEN-1-60.0/60.7 Federal Project: STP-P001(476) ACBR-P001(476) Progress payment No. 05 Payment period ending: 09-20-02 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01912 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,692,102.07 916,005.05 2.a. Extra Work 163,657.58 -452.94 b. Adjustment Comp. -2,432.00 -2,432.00 3. Materials on Hand 343,364.02 -261,871.13 4. Earned Subject to Retention 4,196,691.67 651,248.98 5. Mobilization 2,167,977.00 0.00 6. Total Work Completed 6,021,304.65 7. Deductions -20,000.00 -7,568.00 8. a.Contract Retentions -419,669.17 -65,124.90 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,924,999.50 578,556.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 578,556.08