Dept. of Trans. PROGRESS Serial No. Contract No. 02-295-11-02 01-378014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 23% 16% 01-MEN-1-60.0/60.7 Federal Project: STP-P001(476) ACBR-P001(476) Progress payment No. 06 Payment period ending: 10-20-02 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01912 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,869,381.92 1,177,279.85 2.a. Extra Work 204,187.82 40,530.24 b. Adjustment Comp. -2,432.00 0.00 3. Materials on Hand 229,787.98 -113,576.04 4. Earned Subject to Retention 5,300,925.72 1,104,234.05 5. Mobilization 2,167,977.00 0.00 6. Total Work Completed 7,239,114.74 7. Deductions -20,000.00 0.00 8. a.Contract Retentions -530,092.57 -110,423.40 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,918,810.15 993,810.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 993,810.65