Dept. of Trans. PROGRESS Serial No. Contract No. 02-354-12-54 01-378014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 33% 21% 01-MEN-1-60.0/60.7 Federal Project: STP-P001(476) ACBR-P001(476) Progress payment No. 08 Payment period ending: 12-20-02 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01912 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,304,233.47 1,294,648.64 2.a. Extra Work 312,090.92 41,064.55 b. Adjustment Comp. -2,432.00 0.00 3. Materials on Hand 362,675.31 -104,184.14 4. Earned Subject to Retention 7,976,567.70 1,231,529.05 5. Mobilization 2,746,104.20 0.00 6. Total Work Completed 10,359,996.59 7. Deductions -10,000.00 10,000.00 8. a.Contract Retentions -576,861.51 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 10,135,810.39 1,241,529.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,241,529.05