Dept. of Trans. PROGRESS Serial No. Contract No. 03-021-15-14 01-378014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 34% 22% 01-MEN-1-60.0/60.7 Federal Project: STP-P001(476) ACBR-P001(476) Progress payment No. 09 Payment period ending: 01-17-03 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01912 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,804,783.42 500,549.95 2.a. Extra Work 332,391.39 20,300.47 b. Adjustment Comp. -48,704.00 -46,272.00 3. Materials on Hand 445,542.91 82,867.60 4. Earned Subject to Retention 8,534,013.72 557,446.02 5. Mobilization 2,746,104.20 0.00 6. Total Work Completed 10,834,575.01 7. Deductions -30,000.00 -20,000.00 8. a.Contract Retentions -576,861.51 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 10,673,256.41 537,446.02 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 537,446.02