Dept. of Trans. PROGRESS Serial No. Contract No. 03-083-15-27 01-378014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 37% 26% 01-MEN-1-60.0/60.7 Federal Project: STP-P001(476) ACBR-P001(476) Progress payment No. 11 Payment period ending: 03-20-03 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01912 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,749,848.32 483,031.75 2.a. Extra Work 364,109.66 6,634.30 b. Adjustment Comp. -48,704.00 0.00 3. Materials on Hand 804,481.29 24,174.88 4. Earned Subject to Retention 9,869,735.27 513,840.93 5. Mobilization 2,746,104.20 0.00 6. Total Work Completed 11,811,358.18 7. Deductions -50,000.00 0.00 8. a.Contract Retentions -576,861.51 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,988,977.96 513,840.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 513,840.93