Dept. of Trans. PROGRESS Serial No. Contract No. 03-112-13-37 01-378014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 40% 29% 01-MEN-1-60.0/60.7 Federal Project: STP-P001(476) ACBR-P001(476) Progress payment No. 12 Payment period ending: 04-20-03 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01912 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,664,319.27 914,470.95 2.a. Extra Work 395,144.20 31,034.54 b. Adjustment Comp. -48,704.00 0.00 3. Materials on Hand 720,132.53 -84,348.76 4. Earned Subject to Retention 10,730,892.00 861,156.73 5. Mobilization 2,746,104.20 0.00 6. Total Work Completed 12,756,863.67 7. Deductions -30,000.00 20,000.00 8. a.Contract Retentions -576,861.51 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,870,134.69 881,156.73 10. Reduction Amt to Escrow 11. Payment to Escrow 576,860.00 12. Net Pymt. this Estimate 881,156.73