Dept. of Trans. PROGRESS Serial No. Contract No. 03-143-08-22 01-378014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 44% 32% 01-MEN-1-60.0/60.7 Federal Project: STP-P001(476) ACBR-P001(476) Progress payment No. 13 Payment period ending: 05-20-03 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01912 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,703,403.87 1,039,084.60 2.a. Extra Work 397,514.26 2,370.06 b. Adjustment Comp. -4,797.67 43,906.33 3. Materials on Hand 738,423.47 18,290.94 4. Earned Subject to Retention 11,834,543.93 1,103,651.93 5. Mobilization 2,746,104.20 0.00 6. Total Work Completed 13,842,224.66 7. Deductions -20,000.00 10,000.00 8. a.Contract Retentions -591,727.20 -14,865.69 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 13,968,920.93 1,098,786.24 10. Reduction Amt to Escrow 11. Payment to Escrow 591,720.00 12. Net Pymt. this Estimate 1,098,786.24