Dept. of Trans. PROGRESS Serial No. Contract No. 03-296-15-01 01-378014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 69% 48% 01-MEN-1-60.0/60.7 Federal Project: STP-P001(476) ACBR-P001(476) Progress payment No. 18 Payment period ending: 10-20-03 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01912 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,496,626.17 2,615,137.95 2.a. Extra Work 500,095.07 1,912.50 b. Adjustment Comp. -1,132.77 3,723.84 3. Materials on Hand 258,520.78 -157,798.50 4. Earned Subject to Retention 19,254,109.25 2,462,975.79 5. Mobilization 2,890,636.00 0.00 6. Total Work Completed 21,886,224.47 7. Deductions -20,000.00 0.00 8. a.Contract Retentions -962,705.46 -123,148.79 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 21,162,039.79 2,339,827.00 10. Reduction Amt to Escrow 11. Payment to Escrow 962,700.00 12. Net Pymt. this Estimate 2,339,827.00