Dept. of Trans. PROGRESS Serial No. Contract No. 05-053-12-45 01-378014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 94% 87% 01-MEN-1-60.0/60.7 Federal Project: STP-P001(476) ACBR-P001(476) Progress payment No. 34 Payment period ending: 02-18-05 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01912 Total Estimate This Estimate 1. Contract Itms Without Mobil. 26,865,047.26 110,455.00 2.a. Extra Work 1,301,869.36 60,008.64 b. Adjustment Comp. 148,160.89 34,547.50 3. Materials on Hand 26,912.83 -18,289.33 4. Earned Subject to Retention 28,341,990.34 186,721.81 5. Mobilization 2,890,636.00 0.00 6. Total Work Completed 31,205,713.51 7. Deductions -40,000.00 0.00 8. a.Contract Retentions -1,417,099.52 -9,336.09 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 29,775,526.82 177,385.72 10. Reduction Amt to Escrow 11. Payment to Escrow 1,417,090.00 12. Net Pymt. this Estimate 177,385.72