Dept. of Trans. FINAL Serial No. Contract No. 08-039-13-48 01-378014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 01-MEN-1-60.0/60.7 Federal Project: STP-P001(476) ACBR-P001(476) Progress payment No. 57 Payment period ending: 09-27-06 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01912 Total Estimate This Estimate 1. Contract Itms Without Mobil. 28,053,983.05 0.00 2.a. Extra Work 2,740,975.91 28,597.49 b. Adjustment Comp. 374,056.80 -12,541.23 3. Materials on Hand 4. Earned Subject to Retention 31,169,015.76 16,056.26 5. Mobilization 2,890,636.00 0.00 6. Total Work Completed 34,059,651.76 7. Deductions -10,658.00 0.00 8. a.Contract Retentions -1,538,854.31 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 1,538,854.31 0.00 9. Total pay to Contractor 34,048,993.76 16,056.26 10. Reduction Amt to Escrow -1,538,660.00 0.00 11. Payment to Escrow 1,538,660.00 12. Net Pymt. this Estimate 16,056.26