Dept. of Trans. PROGRESS Serial No. Contract No. 15-264-14-03 01-378144 PROGRESS PAYMENT VOUCHER %complete: %time: 40% 33% Location: Federal Project: 01-MEN-128-10.6/23.3 NONE Progress payment No. 002 Payment period ending: 09-20-15 GRANITE CONSTRUCTION COMPANY 1324 S. STATE STREET UKIAH CA 95482 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 243,134.89 194,558.06 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 243,134.89 194,558.06 5. Mobilization 61,000.45 28,894.95 6. Total Work Completed 304,135.34 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 304,135.34 223,453.01 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 223,453.01