Dept. of Trans. PROGRESS Serial No. Contract No. 14-234-07-25 01-378164 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 17% 22% 01-MEN-128-14.3/40.6 Federal Project: STP-P128(52) Progress payment No. 03 Payment period ending: 08-20-14 ARGONAUT CONSTRUCTORS PO BOX 639 SANTA ROSA CA 95402 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 524,309.37 361,248.63 2.a. Extra Work 35,486.41 35,486.41 b. Adjustment Comp. -3,405.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 556,390.78 396,735.04 5. Mobilization 115,500.00 38,500.00 6. Total Work Completed 671,890.78 7. Deductions -90,312.15 -88,312.15 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 581,578.63 346,922.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 346,922.89