Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 07-213-13-21 01-385704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 37% 24% 01-MEN-1-69.4/70.1 Federal Project: ACST-P001(529) P-P001(529) ACBR-P001(529) Progress payment No. 08 Payment period ending: 07-20-07 GOLDEN STATE BRIDGE INC 901 HOWE ROAD MARTINEZ CA 94553 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,858,643.97 109,200.00 2.a. Extra Work 239,771.83 0.00 b. Adjustment Comp. 329,376.32 0.00 3. Materials on Hand 227,675.95 0.00 4. Earned Subject to Retention 12,655,468.07 109,200.00 5. Mobilization 3,990,000.00 0.00 6. Total Work Completed 16,417,792.12 7. Deductions -10,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 16,635,468.07 109,200.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 109,200.00