Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 08-063-16-05 01-385704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 01-MEN-1-69.4/70.1 Federal Project: ACST-P001(529) P-P001(529) ACBR-P001(529) Progress payment No. 17 Payment period ending: 02-20-08 GOLDEN STATE BRIDGE INC 901 HOWE ROAD MARTINEZ CA 94553 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 21,030,442.22 221,498.28 2.a. Extra Work 1,992,942.28 798.46 b. Adjustment Comp. 329,376.32 0.00 3. Materials on Hand 332,201.59 0.00 4. Earned Subject to Retention 23,684,962.41 222,296.74 5. Mobilization 4,200,000.00 0.00 6. Total Work Completed 27,552,760.82 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 27,884,962.41 222,296.74 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 222,296.74