Dept. of Trans. PROGRESS Serial No. Contract No. 05-355-16-33 01-395914 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 84% 01-HUM-299-R21.8/42.6 Federal Project: NONE Progress payment No. 06 Payment period ending: 12-20-05 R BROWN CONSTRUCTION COMPANY INC P O BOX 406 WILLOW CREEK CA 95573 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 241,704.54 3,164.00 2.a. Extra Work 31,927.55 7,390.67 b. Adjustment Comp. 55,501.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 329,133.09 10,554.67 5. Mobilization 30,000.00 0.00 6. Total Work Completed 359,133.09 7. Deductions 8. a.Contract Retentions -16,456.65 -527.73 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 342,676.44 10,026.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,026.94