Dept. of Trans. SEMI-FINAL Serial No. Contract No. 17-088-15-19 01-397514 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 01-MEN-101-98.9/R100.8 ER-37B3(4) Progress payment No. 053 Payment period ending: 12-31-09 MCM CONSTRUCTION INC PO BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 61,111,063.70 1,781.25 2. a. Extra Work 5,394,524.33 0.00 b. Adustment Comp. 2,392,288.59 0.00 3. Materials on Hand 4. Earned Subject to Retention 68,897,876.62 1,781.25 5. Mobilization 6,198,627.00 0.00 6. Total Work Completed 75,096,503.62 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 75,086,503.62 1,781.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,781.25