Dept. of Trans. PROGRESS Serial No. Contract No. 12-052-10-58 01-3986U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 24% 50% 01-LAK-53-2.8/7.5 Federal Project: NH-P053(24) Progress payment No. 09 Payment period ending: 02-17-12 SIERRA EQUIPMENT RENTAL INC 8176 ROAD 44 GLENN CA 95943 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,837,297.46 6,068.00 2.a. Extra Work 555,245.42 12,126.54 b. Adjustment Comp. -3,999.38 0.00 3. Materials on Hand 46,675.95 0.00 4. Earned Subject to Retention 2,435,219.45 18,194.54 5. Mobilization 507,300.00 0.00 6. Total Work Completed 2,895,843.50 7. Deductions -20,000.00 -14,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,922,519.45 4,194.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,194.54