Dept. of Trans. PROGRESS Serial No. Contract No. 12-142-11-19 01-3994U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 69% 51% 01-LAK-175-4.9/28.0 Federal Project: 01-LAK-29-0.0/11.9 ACST-000C(339) 01-MEN-175-0.0/9.9 P-000C(339) Progress payment No. 11 Payment period ending: 05-17-12 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,384,959.68 161,805.00 2.a. Extra Work 964,079.09 2,650.21 b. Adjustment Comp. -121,583.06 0.00 3. Materials on Hand 0.00 -65,417.28 4. Earned Subject to Retention 11,227,455.71 99,037.93 5. Mobilization 718,145.00 0.00 6. Total Work Completed 11,945,600.71 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,945,600.71 99,037.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 99,037.93