Dept. of Trans. PROGRESS Serial No. Contract No. 17-171-13-43 01-402814 PROGRESS PAYMENT VOUCHER %complete: %time: 1% 5% Location: Federal Project: 01-MEN-101-50.1/R84.6 ACNH-Q101(309) Progress payment No. 002 Payment period ending: 06-20-17 WYLATTI RESOURCE MANAGEMENT INC PO BOX 575 COVELO CA 95428 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 28,500.00 24,750.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 28,500.00 24,750.00 5. Mobilization 6. Total Work Completed 28,500.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 28,500.00 24,750.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 24,750.00