Dept. of Trans. PROGRESS Serial No. Contract No. 18-030-10-33 01-402814 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 96% Location: Federal Project: 01-MEN-101-50.1/R84.6 ACNH-Q101(309) Progress payment No. 009 Payment period ending: 01-20-18 WYLATTI RESOURCE MANAGEMENT INC PO BOX 575 COVELO CA 95428 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,792,421.24 -9,818.76 2. a. Extra Work 176,074.29 57,080.39 b. Adustment Comp. -500.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,967,995.53 47,261.63 5. Mobilization 51,709.00 0.00 6. Total Work Completed 2,019,704.53 7. Deductions -3,500.00 2,500.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,016,204.53 49,761.63 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 49,761.63