Dept. of Trans. PROGRESS Serial No. Contract No. 05-206-13-14 01-412204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 33% 64% 01-MEN-101-R84.0/ .0 Federal Project: NONE Progress payment No. 04 Payment period ending: 07-20-05 SONOMA ENGINEERING INC 110 DRY CREEK ROAD HEALDSBURG CA 95448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 116,740.99 69,136.40 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 116,740.99 69,136.40 5. Mobilization 42,750.00 9,000.00 6. Total Work Completed 159,490.99 7. Deductions -14,000.00 -1,500.00 8. a.Contract Retentions -8,816.22 -4,055.76 b. Unsatisfactory Prog. -2,857.88 -2,857.88 c. Reduction after 95% Comp. 9. Total pay to Contractor 133,816.89 69,722.76 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 69,722.76