Dept. of Trans. SEMI-FINAL Serial No. Contract No. 02-050-11-07 01-414504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 01-MEN-101-R9.3/17.5 Federal Project: ACST-P101(972) PHG-P101(972) Progress payment No. 04 Payment period ending: 09-07-01 PARNUM PAVING INC 1324 SOUTH STATE STREET UKIAH CA 95482 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 329,725.98 0.00 2.a. Extra Work 27,360.60 14,631.93 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 357,086.58 14,631.93 5. Mobilization 6. Total Work Completed 357,086.58 7. Deductions -69,721.26 0.00 8. a.Contract Retentions -10,376.79 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 10,376.79 0.00 9. Total pay to Contractor 287,365.32 14,631.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 14,631.93