Dept. of Trans. PROGRESS Serial No. Contract No. 07-205-12-24 01-4146V4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 29% 18% 01-LAK-20-38.5/42.0 Federal Project: ACST-P020(142) PH-P020(142) Progress payment No. 05 Payment period ending: 07-20-07 ARGONAUT CONSTRUCTORS P O BOX 639 SANTA ROSA CA 95402 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,404,429.77 1,320,942.71 2.a. Extra Work 80,264.83 38,400.69 b. Adjustment Comp. -1,411.98 0.00 3. Materials on Hand 438,772.34 438,772.34 4. Earned Subject to Retention 3,922,054.96 1,798,115.74 5. Mobilization 1,151,400.00 242,400.00 6. Total Work Completed 4,634,682.62 7. Deductions -427,473.18 -327,473.18 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,645,981.78 1,713,042.56 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,713,042.56