Dept. of Trans. PROGRESS Serial No. Contract No. 07-234-17-31 01-423804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 40% 35% 01-HUM-299-R8.8/R9.0 Federal Project: NONE Progress payment No. 02 Payment period ending: 08-20-07 KERNEN CONSTRUCTION P O BOX 1340 BLUE LAKE CA 95525 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 154,736.50 143,361.50 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 154,736.50 143,361.50 5. Mobilization 29,450.00 29,450.00 6. Total Work Completed 184,186.50 7. Deductions 8. a.Contract Retentions -8,601.99 -7,464.49 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 175,584.51 165,347.01 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 165,347.01