Dept. of Trans. PROGRESS Serial No. Contract No. 04-295-14-27 01-425604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 01-MEN-1-74.1/ .0 Federal Project: NONE Progress payment No. 04 Payment period ending: 10-20-04 K M F CONSTRUCTION P O BOX 5486 SHASTA LAKE CA 96089 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 230,301.00 71,364.50 2.a. Extra Work b. Adjustment Comp. 787.03 0.00 3. Materials on Hand 4. Earned Subject to Retention 231,088.03 71,364.50 5. Mobilization 25,000.00 0.00 6. Total Work Completed 256,088.03 7. Deductions 8. a.Contract Retentions -11,554.40 -3,568.22 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 244,533.63 67,796.28 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 67,796.28