Dept. of Trans. PROGRESS Serial No. Contract No. 05-021-17-05 01-425604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 01-MEN-1-74.1/ .0 Federal Project: NONE Progress payment No. 08 Payment period ending: 01-20-05 K M F CONSTRUCTION P O BOX 5486 SHASTA LAKE CA 96089 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 257,816.75 3,680.00 2.a. Extra Work 107.31 107.31 b. Adjustment Comp. -10,907.46 0.00 3. Materials on Hand 4. Earned Subject to Retention 247,016.60 3,787.31 5. Mobilization 25,000.00 0.00 6. Total Work Completed 272,016.60 7. Deductions 8. a.Contract Retentions -12,350.83 -189.37 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 259,665.77 3,597.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,597.94