Dept. of Trans. PROGRESS Serial No. Contract No. 05-171-14-00 01-425604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 01-MEN-1-74.1/ .0 Federal Project: NONE Progress payment No. 12 Payment period ending: 06-20-05 K M F CONSTRUCTION P O BOX 5486 SHASTA LAKE CA 96089 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 273,496.75 3,200.00 2.a. Extra Work 374.93 0.00 b. Adjustment Comp. -10,599.11 0.00 3. Materials on Hand 4. Earned Subject to Retention 263,272.57 3,200.00 5. Mobilization 25,000.00 0.00 6. Total Work Completed 288,272.57 7. Deductions -1,500.00 -1,500.00 8. a.Contract Retentions -13,163.63 -160.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 273,608.94 1,540.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,540.00