Dept. of Trans. PROGRESS Serial No. Contract No. 05-263-17-18 01-425604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 01-MEN-1-74.1/ .0 Federal Project: NONE Progress payment No. 15 Payment period ending: 09-20-05 K M F CONSTRUCTION P O BOX 5486 SHASTA LAKE CA 96089 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 285,016.75 3,840.00 2.a. Extra Work 374.93 0.00 b. Adjustment Comp. -10,599.11 0.00 3. Materials on Hand 4. Earned Subject to Retention 274,792.57 3,840.00 5. Mobilization 25,000.00 0.00 6. Total Work Completed 299,792.57 7. Deductions 8. a.Contract Retentions -13,739.63 -192.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 286,052.94 3,648.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,648.00