Dept. of Trans. PROGRESS Serial No. Contract No. 07-170-10-26 01-426104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 97% 78% 01-HUM-5712 Federal Project: NONE Progress payment No. 08 Payment period ending: 06-15-07 ROADWAY ELECTRICAL WORKS INCORPORATED P O BOX 5083 MODESTO CA 95352 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 746,130.00 37,730.00 2.a. Extra Work b. Adjustment Comp. 13,207.47 13,207.47 3. Materials on Hand 4. Earned Subject to Retention 759,337.47 50,937.47 5. Mobilization 6. Total Work Completed 759,337.47 7. Deductions 8. a.Contract Retentions -37,966.87 -2,546.87 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 721,370.60 48,390.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 48,390.60