Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 20-010-12-44 01-427804 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 01-LAK-20-1.0/46.3 B1NH-X033(90) 01-LAK-29-6.1/48.8 Progress payment No. 013 Payment period ending: 11-22-19 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,951,235.89 -33,211.45 2. a. Extra Work 441,902.62 4,801.47 b. Adustment Comp. -142,932.49 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,250,206.02 -28,409.98 5. Mobilization 316,000.00 0.00 6. Total Work Completed 3,566,206.02 7. Deductions -25,000.00 -25,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,541,206.02 -53,409.98 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -53,409.98