Dept. of Trans. PROGRESS Serial No. Contract No. 07-234-17-38 01-432004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 41% 20% 01-MEN-162-5.0/5.2 Federal Project: NONE Progress payment No. 01 Payment period ending: 08-20-07 GOODWIN CONSTRUCTION INC 460 N YOSEMITE AVE SUITE 4 OAKDALE CA 95361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 166,919.00 166,919.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 166,919.00 166,919.00 5. Mobilization 9,500.00 9,500.00 6. Total Work Completed 176,419.00 7. Deductions 8. a.Contract Retentions -8,447.20 -8,447.20 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 167,971.80 167,971.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 167,971.80