Dept. of Trans. SEMI-FINAL Serial No. Contract No. 10-069-16-36 01-432604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 01-LAK-20-R9.4/R12.1 Federal Project: OTS-05(18) Progress payment No. 17 Payment period ending: 12-29-09 ARGONAUT CONSTRUCTORS P O BOX 639 SANTA ROSA CA 95402 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,233,541.67 0.00 2.a. Extra Work 637,168.50 8,206.77 b. Adjustment Comp. -175,048.69 0.00 3. Materials on Hand 4. Earned Subject to Retention 6,695,661.48 8,206.77 5. Mobilization 600,000.00 0.00 6. Total Work Completed 7,295,661.48 7. Deductions -269,100.00 246,900.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,026,561.48 255,106.77 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 255,106.77