Dept. of Trans. SEMI-FINAL Serial No. Contract No. 08-148-10-43 01-432704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 01-MEN-253-1.1/1.3 Federal Project: NONE Progress payment No. 07 Payment period ending: 03-24-08 STEVE MANNING CONSTRUCTION INC P O BOX 491660 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 544,601.60 0.00 2.a. Extra Work 121,420.15 73,147.13 b. Adjustment Comp. 3,238.26 0.00 3. Materials on Hand 4. Earned Subject to Retention 669,260.01 73,147.13 5. Mobilization 32,000.00 0.00 6. Total Work Completed 701,260.01 7. Deductions -1,000.00 0.00 8. a.Contract Retentions -28,875.39 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 28,875.39 0.00 9. Total pay to Contractor 700,260.01 73,147.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 73,147.13