Dept. of Trans. PROGRESS Serial No. Contract No. 08-357-15-44 01-434604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 01-MEN-5710 Federal Project: NONE Progress payment No. 17 Payment period ending: 12-19-08 BRCO CONSTRUCTORS INC P O BOX 367 LOOMIS CA 95650 Escrow No. 02306 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,064,312.84 180,742.40 2.a. Extra Work 350,325.08 5,262.80 b. Adjustment Comp. 79,172.05 -38,295.06 3. Materials on Hand 4. Earned Subject to Retention 7,493,809.97 147,710.14 5. Mobilization 6. Total Work Completed 7,493,809.97 7. Deductions -35,894.20 -18,956.70 8. a.Contract Retentions -374,690.50 -7,385.51 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,083,225.27 121,367.93 10. Reduction Amt to Escrow 11. Payment to Escrow 374,690.00 12. Net Pymt. this Estimate 121,367.93