Dept. of Trans. PROGRESS Serial No. Contract No. 09-113-08-01 01-434604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 01-MEN-5710 Federal Project: NONE Progress payment No. 21 Payment period ending: 04-20-09 BRCO CONSTRUCTORS INC P O BOX 367 LOOMIS CA 95650 Escrow No. 02306 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,275,443.49 151,954.90 2.a. Extra Work 420,046.81 0.00 b. Adjustment Comp. 79,172.05 0.00 3. Materials on Hand 4. Earned Subject to Retention 7,774,662.35 151,954.90 5. Mobilization 6. Total Work Completed 7,774,662.35 7. Deductions -20,894.20 -6,000.00 8. a.Contract Retentions -388,733.12 -7,597.75 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,365,035.03 138,357.15 10. Reduction Amt to Escrow 11. Payment to Escrow 388,730.00 12. Net Pymt. this Estimate 138,357.15