Dept. of Trans. PROGRESS Serial No. Contract No. 09-168-08-24 01-434604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 01-MEN-5710 Federal Project: NONE Progress payment No. 23 Payment period ending: 06-19-09 BRCO CONSTRUCTORS INC P O BOX 367 LOOMIS CA 95650 Escrow No. 02306 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,278,462.24 1,431.75 2.a. Extra Work 500,932.19 0.00 b. Adjustment Comp. 63,926.03 -15,246.02 3. Materials on Hand 42,000.00 42,000.00 4. Earned Subject to Retention 7,885,320.46 28,185.73 5. Mobilization 6. Total Work Completed 7,843,320.46 7. Deductions -14,894.20 15,245.92 8. a.Contract Retentions -394,266.02 -1,409.28 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,476,160.24 42,022.37 10. Reduction Amt to Escrow 11. Payment to Escrow 394,260.00 12. Net Pymt. this Estimate 42,022.37